Coal Handling Upgrade Phase II

Westar Energy
Lawrence, Kansas

Westar Energy
Dale Larson
P.O. Box 889
Topeka, Kansas 66601
P: (785) 575-6426 F: (785) 575-1910

Completed: May 2005

Scope of Work: This project consisted of upgrading the Primary Coal Handling System. The work included modifications and additions to existing buildings, structures and supports, as well as the replacement of existing coal processing and handling equipment (crushers, chutes, conveyors, hoppers, feeders, etc.).

Back to Industrial