Food Processing

Marion, Ohio

Wenck Associates, Inc.
Tim Colliton
PO Box 249
Maple Plain, Minnesota 55359
P: (763) 479-4236 F: (763) 479-4242

Completed: June 2006

Scope of Work: The project scope was the conversion of HVAC and exhaust equipment associated with a confidential process room that operates 7 x 24. For the HVAC conversion, two existing 60 ton roof top units were replaced with a York 150 ton air cooled chiller and make up air handler designed for the supply of 100% outside air. The exhaust conversion consisted of replacing two 5,000 cfm fans with three new systems. One fan at 2,400 cfm, one at 8,400 cfm and one at 22,500 cfm resulting in a complete air exsub_industrial in the process room every 3 minutes. To facilitate this air exchange, custom manufactured stainless steel ductwork, filter boxes, and exhaust hoods were installed.

Work was conducted in parallel with plant operations until a predetermined conversion date. The conversion was scheduled over a holiday weekend with 72 hours of downtime available. After approximately 45 hours of process related piping and ductwork replacement, all systems were commissioned and turned over to the owner.

Back to Industrial